Notification of proposed crane or construction near the airport allows the Federal Aviation Administration (FAA) and airport operations to identify potential aeronautical hazards. Before erecting any crane, mobile or otherwise, please read the following information below to see if your project meets any of the criteria requisite to filing a FAA Form 7460-1.
For new construction and/or construction using cranes within close proximity to McKinney National Airport, please use the following information to submit an FAA Form 7460-1, Notice of Proposed Construction or Alteration, prior to construction. Use the Notice Criteria Tool to enter information on any potential obstructions. Please note this process may take up to 90 days.
If you have additional questions, please contact McKinney National Airport Operations at 972-562-4096.
An FAA Form 7460-1 is required if ANY of the following criteria are met: